The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,600 units per 40-hour workweek.
TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS
A. 24, -
B. 28, A
C. 14, A
D. 14, A
E. 10, B,C
F. 27, D,E
C) The total idle time per cycle for the process is?? (whole number)
TASK, WORKSTATION NUMBER
A. STATION 1
B. STATION 2
C. STATION 3
D. STATION 4
E. STATION 4
F. STATION 5
D) The efficiency of the assembly line with 5 work stations equals??(one decimal place)
E) If one used 6 work stations instead of 5, the efficiency of the assembly line would be what??(one decimal place)