Problem:

The above earned value (EV) chart indicates that the project is:
A. running ahead of schedule and under budget
B. running late and under budget
C. running ahead of schedule and over budget
D. running late and over budget
Summary of question:
This multiple choice question basically belongs to Finance as well as it discusses about the indicators of an Earned Value chart.