Question 1. Here are two types of constraints that a projects face "Technical and Resource constraints". Provide examples and suggest ways to address these constraints.
Question 2. When resource-leveling a project, a number of heuristics can help us prioritize those activities that should receive resources first. Explain how each of the following heuristics works and give an example:
Activities with the smallest slack
Activities with the smallest duration
Activities with the lowest identification number
Activities with the most successor tasks
Activities requiring the most resources