The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,045. A total of 42 direct labor-hours and 255 machine-hours were worked on the job. The direct labor wage rate is $19 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $21 per machine-hour. The total cost for the job on its job cost sheet would be:
- $10,343
- $8,198
- $5,573
- $5,154