Task time estimates for the modification of an assembly


Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

ACTIVITY

TIME IN (HOURS)

IMMEDIATE PREDECESSORS

A

6.0

-

B

7.2

-

C

5.0

A

D

6.0

B, C

E

4.5

B, C

F

7.7

D

G

4.0

E, F

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?

d) Draw a Gantt chart for the project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Task time estimates for the modification of an assembly
Reference No:- TGS02152889

Expected delivery within 24 Hours