Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows-

a) 6.0 -

b) 7.2 -

c) 5.0 a

d) 6.0 b,c

e) 4.5 b,c

f) 7.7 d

g) 4.0 e,f

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?