A project is made up of several tasks, as shown in the table below.
Task Predecessor Duration (days)
A - 7
B - 5
C A 6
D A 8
E B 9
F C 5
G D, E 4
The project is scheduled to begin on Monday, Dec 11, 2017.
Use MS Project to develop the project schedule. Obtain printouts of the Gantt Chart and the Network Diagram