Sweetbay supermarket's new project has initial cost is $5000 and it is expected to provide after tax operating cash flows of $2800 in year 1, $1900 in year 2, $2000 in year 3 and $1800 in year 4. The cost of capital for the project is 15%.
a) What is the payback period for the project?
b) What is the discounted payback period for the project?