Suppose your firm produces a product, and the first unit takes 600 hours to produce, and the fifth takes 262 hours to produce, if the learning continues at the same rate for the foreseeable future, how many total hours to produce the next 60 units. (Round b to 3 decimals, and round L and total hours to two decimals)