Suppose the projections given for price quantity variable


We are evaluating a project that costs $1,140,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 51,000 units per year. Price per unit is $42, variable cost per unit is $20, and fixed costs are $720,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent.

Calculate the best-case and worst-case NPV figures.