Suppose the project network is given and the critical path


Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activity is given. You have been asked by your supervisor to prepare a research paper that addresses the follow criteria:

1. If the project is to be shortened by four days, what is the process to determine which activities, in order of reduction, would be shortened and the resulting cost.

2. What are the project cost and the requirements for its determination and application in a production facility.

3. Analyze implications of changes in the parameters of project timing and cost determination.

4. Evaluate application of project cost and timing concepts on a firm's business operations.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Suppose the project network is given and the critical path
Reference No:- TGS01526082

Expected delivery within 24 Hours