suppose the length of critical path in a project
Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing the project is 95%? Round the answer to the nearest higher integer.
Expected delivery within 24 Hours
please explain how this works im so confusedsuppose spt rule is being used in a dynamic scheduling problem there are five jobs a b c d and e ready to
a machine shop has two machines m1 and m2 four jobs a b c and d need to be processed through machines m1 first and m2 second job a will take one hour
a single machine work center has five jobs assigned to it they are labelled in the order of their arrival in the shop as jobs a b c d and e the work
a single machine work center has five jobs assigned to it they are labeled in the order of their arrival in the shop as jobs a b c d and e the work
suppose the length of critical path in a project is 40 days and the standard deviation is 2 days what due date should be set for the project so that
suppose spt rule is being used in a dynamic scheduling problem there are five jobs abcd and e ready to be processed at the present time the
do you believe that managers should be given more autonomy to make personnel decisions such as hiring appraising and compensating subordinates or do
leaders and their leadership stylesthis week you learned about a number of different leadership theories choose two of todays leaders listed below
discuss potential key changes in technology communications and competition that sigma will face in the future which will have the most impact on
1937844
Questions Asked
3,689
Active Tutors
1459481
Questions Answered
Start Excelling in your courses, Ask a tutor for help and get answers for your problems !!
What types of unconscious or implicit bias might be present? How could they shape people's actions, decisions, or access to resources?
Identify factors that lead to poor performance in STEM by most schools. How can INSET programs be used to improve teacher's pedagody in STEM?
In this week's video, what stood out the most to me was how clearly research separates what "looks helpful" from what actually works.
Problem: Re-word but keep the same content - Social pedagogy is evident in schools through a strong focus on relationships,
Describe a social condition in your community or the community of someone you know. How did that social condition motivate active citizens to exercise
Please provide a response with APA citations and references to "When we talk about stigma related to people with psychological disorders
Communication, creativity and decision-making skills are essential to daily life. In this course, you learned about the development of language