Question: Below durations, what activities each must precede and the crash cost to reduce duration per? week:
Activity |
Duration |
Precedes |
Crash cost |
A |
2 |
B,C |
300 |
B |
2 |
E |
100 |
C |
4 |
F |
175 |
E |
1 |
F |
140 |
F |
2 |
|
400 |
Suppose that you have 5 weeks? (instead of 8)to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.