Question: BUILDING TEAM SKILLS
Suppose that you are planning to build a house in the country. It will be a brick, one-story structure of approximately 2,000 square feet, centrally heated and cooled. It will have three bedrooms, two bathrooms, a family room, a dining room, a kitchen with a breakfast nook, a study, a utility room, an entry foyer, a two-car garage, a covered patio, and a fireplace. Appliances will operate on electricity and propane fuel. You have received approval and can be connected to the cooperative water system at any time. Public sewerage services are not available; therefore, you must rely on a septic system. You want to know how long it will take to build the house.
Assignment: 1. Identify the major activities involved in the project and sequence them in the proper order.
2. Estimate the time required for each activity and establish the critical path.
3. Working in a group, prepare a PERT diagram to show the steps involved in building your house.
4. Present your PERT diagram to the class and ask for comments and suggestions.