Suppose that the time statistician 4 needs to complete the


A market research firm's three clients each requested that the firm conduct a sample survey. Four available statisticians can be assigned to these three projects; however, all four statisticians are busy, and therefore each can handle only one client. The following data show the number of hours required for each statistician to complete each job; the differences in time are based on experience and ability of the statisticians.

Statistician

A

Client B

C

1

150

210

270

2

170

230

220

3

180

230

225

4

160

240

230

a. Formulate and solve a linear programming model for this problem.

b. Suppose that the time statistician 4 needs to complete the job for client A is increased from 160 to 165 hours. What effect will this change have on the solution?

c. Suppose that the time statistician 4 needs to complete the job for client A is decreased to 140 hours. What effect will this change have on the solution?

d. Suppose that the time statistician 3 needs to complete the job for client B increases to 250 hours. What effect will this change have on the solution?