Question: 1. Suppose that the industrial engineers are able to increase the average utilization rate of the CVD tool from 80% to 90%. What is the projected impact of this 10% increase on the PW of the project?
2. Suppose that the mechanical engineer in the plant has retrofitted the CVD tool so that it now produces 15 wafers per hour. What is the new breakeven point?