Suppose that the following estimates of activity times in


Suppose that the following estimates of activity times (in weeks) were provided for the network shown in Problem 6:

Activity

A

Optimistic

4.0

Most Probable

5.0

Pessimistic

6.0

B

2.5

3.0

3.5

C

6.0

7.0

8.0

D

5.0

5.5

9.0

E

5.0

7.0

9.0

F

2.0

3.0

4.0

G

8.0

10.0

12.0

H

6.0

7.0

14.0

What is the probability that the project will be completed

a. Within 21 weeks?

b. Within 22 weeks?

c. Within 25 weeks?

Text Book: An Introduction to Management Science: Quantitative Approaches to Decision. By David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Camm, James Cochran.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Suppose that the following estimates of activity times in
Reference No:- TGS01220260

Expected delivery within 24 Hours