Suppose for the case under consideration in this section ie


Suppose for the case under consideration in this section (i.e., two coherent groups of generators) that we lose all the lines connecting a hypothetical network A to network B at t = 0, and then all the breakers reclose after T seconds. All other factors being equal (or disregarded), what is the most favorable grouping of the