Problem:
Network Model Transportation Problem : Supply Capacity and Demand Satisfaction
Please help with the following problem.
Canning Transport is to move goods from three factories to three distribution centers. Information about the move is given below. Give the network model and the linear programming model for this problem.
Supply at Source Demand at Destination
200 A 250 I
100 B 125 II
150 C 125 III
Source B cannot ship to destination III
Shipping costs are:
I II III
A 3 2 5
B 9 10 12
C 5 6 4