Super Fun Industries manufactures four? top-selling toys code named? A-148, B-356,? B-457, and? C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super? Fun's manufacturing plant is open 18 hours a? day, 5 days a? week, 7 hours on Saturday.
A-148 B-356 B-457 C-843
Processing Time Station 1 5 5 0 7
Processing Time Station 2 3 2 5 3
Processing Time Station 3 7 7 5 3
Processing Time Station 4 2 0 10 1
a. If only toy? A-148 is produced during a specific? week, how many units could be produced. ?(Enter your response rounded down to the nearest whole? number.)