Summer Tyme, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.97 million. The fixed asset will be depreciated straight-line to zero over its 3-year tax life, after which time it will have a market value (salvage value) of $231,000. The project requires an initial investment in net working capital of $330,000. The project is estimated to generate $2,640,000 in annual sales, with costs of $1,056,000. The tax rate is 31 percent and the required return on the project is 8 percent.
Required:
(a) What is the project's year 0 net cash flow?
(b) What is the project's year 1 net cash flow?
(c) What is the project's year 2 net cash flow?
(d) What is the project's year 3 net cash flow?
(e) What is the NPV?