Sub-process a takes five minutes sub-process b takes three


Sub-process A takes five minutes, sub-process B takes three minutes, and the sub-process C, which assembles the inputs from A and B, takes four mintues.

What is the possible daily output of this assebly process, assuming an eight hour work day?

  • 5
  • 40
  • 96
  • 12