Assignment:
The following 5 overhaul jobs are waiting to be processed at Avianic’s Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Assume that all jobs arrived on day 180; today’s date is 200.
Job |
Due Date |
Remaining Time (Days) |
A |
212 |
6 |
B |
209 |
3 |
C |
208 |
3 |
D |
210 |
8 |
In what sequence would the jobs be ranked according to the following decision rules:
a) FCFS b) SPT c) LPT d) EDD e) Critical ratio
Which is best and why? Which has the minimum latenes.
Provide complete and step by step solution for the question and show calculations and use formulas.