Stephen Hall is developing a program in supply chain mgmt certification for mgrs. Hall has listed a number of activities conducted. The activities, immediate predecessors, and times appear in the table: 1). The project length for the leadership training development project is ____ days?
Activity
|
Immediate Predecessor(s)
|
Time (days)
|
A
|
-
|
2
|
B
|
-
|
5
|
C
|
-
|
3
|
D
|
B
|
10
|
E
|
A, D
|
5
|
F
|
C
|
5
|
G
|
E, F
|
8
|