Use the following table to answer the succeeding questions (duration in days):
ACTIVITY
|
DEPENDENCY
|
DURATION
|
A
|
-
|
6
|
B
|
A
|
4
|
C
|
B, E
|
3
|
D
|
-
|
5
|
E
|
A, D
|
2
|
F
|
-
|
1
|
G
|
F
|
7
|
H
|
C,E,G
|
2
|
I
|
G
|
4
|
J
|
C
|
8
|
1. Construct the network diagram.
2. State the critical path.
3. What is the duration of the project?
4. State in table format, the ES, LF and slack for activities E, H and I.
5. What would happen to the project if there is a delay of two (2) days in activities B and F?