CASE 4: SHORT-TERM SCHEDULING
Stan's Furniture Refinishers has 7 items of furniture to sand first and then varnish using the sending and varnishing machines, respectively. The items and their times on these two machines are shown in the table:
Item Sanding time,hrs. Varnishing time,hrs.
A 8 7
B 6 4
C 5 8
D 8 12
E 10 14
F 12 8
G 4 6
Questions.
- Using the Johnson’s rule, identify the optimal sequencing of these jobs. The jobs must go through the machines in the same order starting with the sanding machine.
- Identify the cumulative time for the initial sequencing and for the sequencing based on the Johnson’s rule. Provide the existing sequence chart and Johnson’s rule charts.
- Compare and explain your results.