The following company information is available for January:
Direct materials used..................$2,300 feet @$50 per foot
Standard costs for direct materials for January production ...$2,400 feet @ $48 per foot
The direct material price variance is:
a. $7,600 unfavorable.
b. $6,350 favorable.
c. $4,600 unfavorable.
d. $4,700 favorable.
e. $4,350 favorable.