Some projects have a fixed due date while others have to be finished as early as possible, and the project manager only makes commitments on the completion date once she and her project management team have scheduled the project. Explain how the backward pass differs for these two project types. Explain how it is possible that there can be slack on the critical path. What is the implication of negative slack on the critical path?