Solving for labor hours. Ernie's Engineering Consulting reports the following direct labor information for clerical staff:
Month: April
Standard Rate $15 per Hour
Actual Rate Paid $17 per Hour
Standard Hours Allowed for Actual Production 1,600
Hours Labor Efficiency Variance $860 U
What are the actual hours worked, rounded to the nearest hour?