Problem:
Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows:
Time Required
Step - Description - per Student
1- Unpack and place on belt - 1.0 minute
2 - Strip off bad habits - 1.5 minutes
3 - Scrub and clean mind - 0.8 minute
4 - Insert modern methods - 1.0 minute
5 - Polish and pack - 1.2 minutes
One faculty member is assigned to each of these steps. Faculty members work a 40-hour week and rotate jobs each week. Mr. Rockness has been working on a contract from General Eclectic, which requires delivery of 2,000 refurbished students per week.
A representative of the human resources department has just called complaining that the company hasn't been receiving the agreed-upon number of students. A check of finished goods inventory by Mr. Rockness reveals that there is no stock left.
Required: What is going on? Provide thorough explanation of the given question.