The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and alternators. Both of these products require wiring and testing during the assembly process. Each generator requires 2 hours of wiring and 1 hour of testing and can be sold for a $250 profit. There are 260 hours of wiring time and 140 hours of testing time available in the next production period, and Electrotech wants to maximize profit.
A. Formulate and LP model for this problem
B. Sketch the feasible region for the problem
C. Determine the optimal solution to this problem using level curves.