A senior MIS design class project team has developed following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are needed. Draw project network. Find out the critical path.    

Activity

Time

Immediate Predecessor

A. Find client

4

---

B. Write prospectus

2

A

C. Obtain approval from client and professor

3

B

D. Complete programming

12

C

E. Do industry background research

10

---

F. Write final paper

6

D, E

G. Write oral report

5

D, E

1. In optimal solution, what is critical path?

2. How long will it take to complete project?