Simulate 5 project completion experiences using random


The project network for building a garage is shown in Figure 16.11 and includes data on activity times and their deviations.

a. Develop a Monte Carlo simulation model that can be used to generate a distribution of project completion times (longest path from node 1 to 8).

b. Simulate 5 project completion experiences using random numbers from Appendix B. What is the expected project duration time?