Indicate the following statements are true or false, and explain why each is true or false: Indicate the following statements are true or false, and explain why each is true or false
E. Similar production lines producing the same products can have the same throughput with different levels of WIP
F. The bottleneck station always has the longest processing time
G. The amount of variability in processing times cause the cycle time to increase and the throughput to decrease
H. The practical worst case performance level is the optimum level of performance that is used to evaluate the actual performance of the line and it is fixed when the amount of work in process is changed
I. The push production system promotes larger work in process levels
J. Non-preemptive stops of the machines are not random occurrences?
K. Steady state concept is important in the queueing analysis ?