Show the productivity change, for one month last year


Problem:

The CEO has asked you to evaluate the firm's productivity by comparing performance a month from last year and equivalent month this year. The following data are available:

        

Last   Year

  
  

This   Year

  
  

Output

  
  

12,500   units

  
  

14,100   units

  
  

Labor   (hours)

  
  

11,000   

  
  

11,200

  
  

Utilities   (BTUs)

  
  

7,800

  
  

9,250

  
  

Capital

  
  

$85,000

  
  

$87,000

  

The CEO determines his costs to be as follows:

  • Labor $20 per hour
  • Utilities $1.50 per BTU
  • Capital 15% per month of investment.

Required:

Question 1) Show the productivity change, for one month last year versus one month this year, on a multifactor basis.

Solve the given numerical problem and illustrate step by step calculation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Show the productivity change, for one month last year
Reference No:- TGS0884712

Expected delivery within 24 Hours