Should it be accepted or rejected


Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 2.5 years, respectively.
Time 0 1 2 3 4 5
Cash Flow -125,000 65,000 78,000 105,000 105,000 25,000
Use the NPV decision rule to evaluate this project; should it be accepted or rejected?

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Should it be accepted or rejected
Reference No:- TGS0109490