Shorten the project three weeks by finding the


Table contains information about an environmental clean-up project. Shorten the project three weeks by finding the minimum-costs schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.

TABLE 2.5

ENVIRONMENTAL PROJECT DATA

Activity

Normal Time (weeks)

Crash Time (weeks)

Cost to Crash ($ per week)

Immediate Predecessor($)

A

7

6

200

None

B

12

9

250

None

C

7

6

250

A

D

6

5

300

A

E

1

1

-

B

F

1

1

-

C, D

G

3

1

200

D, E

H

3

2

350

F

I

2

2

-

G