Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation. This is an example of:
- A constraint
- An assumption
- A start-to-finish dependency
- A finish-to-start dependency
Solution: 4. the inspections must be finished before the sheet-rocking can start.