Problem
I. The status report at the end of the 6th month says the project has a CPI of 0.86 and an SPI of 1.25. Is the project on track? Ensure you refer to both the budget and the schedule. Share one recommendation to get the project back on track. (Interpretation and recommendations)
II. The status report at the end of the 6th month says the project has a CPI of 1.15 and an SPI of 0.90. Is the project on track? Ensure you refer to both the budget and the schedule. Share one recommendation to get the project back on track. (Interpretation and recommendations)