Create a Gantt Chart for the following project, and show the Gantt Chart below.
Set a start date of September 1, 2018. Assume that work can be done 5 days per week, with no work done on Saturdays or Sundays.
Identify the Critical Path. When will the project be completed?
Task Number
|
Activity
|
Immediate Precedence
|
Task Duration (Days)
|
1.
|
Strategic Planning Phase
|
none
|
20
|
2.
|
Team Orientation
|
1
|
28
|
3.
|
Software Configuration
|
2
|
60
|
4.
|
Testing
|
3
|
20
|
5.
|
Training
|
2
|
10
|
6.
|
Facility Modification
|
1
|
45
|