Scottso Corporation applies overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $286,500, budgeted machine-hours were 19,100. Actual factory overhead was $320,125, actual machine-hours were 19,700. How much overhead would be applied to production?
$286,500.
$320,125.
$310,375.
$295,500.