Assignment:
Courtney Kamauf schedules production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The table requires a top, four legs, 1/ 8 gallon of stain, 1 /16 gallon of glue, 2 short braces between the legs and 2 long braces between the legs, and a brass cap that goes on the bottom of each leg. She has 100 gallons of glue in inventory, but none of the other components. All items except the brass caps, stain, and glue are ordered on a lot-for-lot basis. The caps are purchased in quantities of 1,000, stain and glue by the gallon. Lead time is 1 day for each item. Schedule the order releases necessary to produce 640 coffee tables on days 5 and 6, and 128 on days 7 and 8.
Provide complete and step by step solution for the question and show calculations and use formulas.