Question:
Six jobs are to be processed through a two-step operation. The first operation involves sanding, the second involves painting. Processing times in hours are as shown (see below). Schedule the jobs.
Job Operation #1 Operation #2
A 10 5
B 7 4
C 5 7
D 3 8
E 2 6
F 4 3