Shown below are two sets of real-time, periodic tasks. For (a), will the schedule produced by the Earliest Deadline First algorithm meet all the deadlines? For (b), will the scheduled produced by the Deadline Monotonic algorithm meet all the deadlines?
Ti si di pi ei
T1 3 4 4 1
T2 1 5 6 2
T3 2 3 3 1
(a)
Ti si di pi ei
T1 0 3 4 1
T2 3 4 4 1
T3 2 2 2 1
(b)