schedule control is concerned with all of the


Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.