Scenario analysis for a proposal new project


Scenario analysis for a proposal new project has resulted in the following:

Worst Case: NPV - ($1,000) Prob. - .2
Most Likely: NPV - 300 Prob. - .3
Best Case: NPV - 600 Prob. .5

An abandonment option would change the NPV in the worst case to (500). The projects expected NPV if the abandonment option is included is?