Problem -
Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 305 days.
Annual demand for steering wheels
|
30,500
|
Daily demand
|
100
|
Daily production (8 hours)
|
800
|
Desired lot size (2 hours of production)
|
200
|
Holding cost per unit per year
|
$10
|
a) What is the setup cost, based on the desired lot size?
b) What is the setup time, based on $40 per hour setup labor?