Review the current status of the project


Assignment:

You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations (releases). Each of the iterations will take 20 days to complete at a cost of $20,000 per iteration. Today is the end of what should be iteration three. The current status of the project is as follows: Iteration One complete, spent $20,000 Iteration Two complete, spent $25,000 Iteration Three half done, spent $17,000 Iteration Four Not started. Please provide the following values: PV, EV, AC, CPI, SPI, EAC, ETC, BAC

Request for Solution File

Ask an Expert for Answer!!
Project Management: Review the current status of the project
Reference No:- TGS02054892

Expected delivery within 24 Hours