Business disruption has become a serious concern of the company president who wants to see a detailed plan before the work begins. She explains that current work must be completed in the old hangar and all new work is to being in the new hangar.
As the project manager, how will you satisfy these requirements for continuity of business?
The president is concerned about the 10-day window. What can you do to reassure her that you can do the job on time?