Question: Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times.
Activity
|
Immediate Predecessor
|
Time
(weeks)
|
A
|
--
|
3
|
B
|
--
|
1
|
C
|
--
|
2
|
D
|
A,B,C
|
4
|
E
|
C,D
|
5
|
F
|
A
|
3
|
G
|
D,F
|
6
|
H
|
E
|
4
|
a. Prepare a project network.
b. Identify the critical activities.
c. Which activity has the most slack time?
d. Will the project be completed by September 1?