Renovation activities and their estimated times


Question: Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building.  The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired.  The condominium manager identified the following renovation activities and their estimated times.

 

Activity

Immediate Predecessor

Time

(weeks)

A

--

3

B

--

1

C

--

2

D

A,B,C

4

E

C,D

5

F

A

3

G

D,F

6

H

E

4


a. Prepare a project network.

b. Identify the critical activities.

c. Which activity has the most slack time?

d. Will the project be completed by September 1?

Solution Preview :

Prepared by a verified Expert
Project Management: Renovation activities and their estimated times
Reference No:- TGS01955714

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)